18/12/2025
The screws for the review units have now been dispatched to FSR and, being sourced in England, are scheduled to arrive tomorrow.
19/12/2025
The screws for the review units have now arrived at FSR and have been formally approved.
02/01/2026
MiKeyDigit has been commissioned to produce product page renders. A partial payment has been issued, with the remaining balance to be settled upon completion.
08/01/2026
MiKeyDigit has now completed the product page renders, and the balance has been remitted in full.
11/01/2026
Requests for production-run quotations have now been issued for all aspects of the project—from bespoke screws to enclosures.
13/01/2026
The green review unit is currently subject to a slight delay; all remaining review units have now been completed and are awaiting assembly. Finished units are scheduled to depart for FSR imminently, with the green review unit to follow in due course upon completion.
Production-run quotations for the PCBs have now been received.
14/01/2026
Production-run quotations for the carry cases have now been received.
19/01/2026
The remaining balance for the review units—comprising the enclosures, switch plates, and authentication crests—has now been settled in full following completion of manufacturing. All completed review units have been prepared for dispatch to FSR; the green review unit is subject to a slight delay and will be dispatched in due course upon completion.
Bespoke shipping boxes have been commissioned in preparation for the group buy. These are custom-made in England and will be ready ahead of fulfilment.
20/01/2026
Prior to final shipment, images of the assembled enclosures were received. Upon subsequent review, a minor corrective refinement was identified. This will result in a slight delay in shipment to FSR.
21/01/2026
The previously identified minor corrective refinement has been largely resolved. All screw holes were sized for M2.5 rather than the intended M3 screws. Exterior case screws have since been updated to M3, while internal screws remain M2.5 for the review units. As a result, replacement plates will be commissioned for the review units to accommodate this change, ensuring that no plate alignment is required. Any minor finish inconsistencies/flaws reflect these quick adjustments. All completed units have now been sent to FSR.
22/01/2026
The prototype unit has been packed and is en route to Chung-Li for a series of typing test videos, designed to highlight the board’s acoustic character in advance of the purchasing period.
Alexotos has been paid in full for content creation relating to the project, for which a review unit will be provided.
24/01/2026
The prototype unit has been received by Chung-Li.
25/01/2026
Sound tests highlighting the board’s acoustic character are now beginning to be shared publicly.
26/01/2026
Production-run quotations for the enclosures, authentication crests, and switch plates have now been received.
Three of the four review units have now arrived at FSR, accompanied by plates and authentication crests. They have passed quality control, with only a minor issue concerning the exterior screw holes, which are no longer anodised following their resizing to M3.
27/01/2026
The bespoke shipping boxes, custom-made in England for this project, have now been dispatched and are due to arrive with us within the next day.
28/01/2026
The bespoke shipping boxes have been received but found to be manufactured to incorrect dimensions and are too small to accommodate the carry cases. This batch has been rejected. Replacement boxes have been confirmed and will be shipped to FSR as soon as possible.
30/01/2026
Tomb has been fully compensated for the modified Cherry switches that will be used in the review units.
The prototype has been repacked and is presently en route back to FSR.
01/02/2026
The group buy has opened—running until 8 March or until our internal unit allocation is fully subscribed.
02/02/2026
The fourth review unit has now been finished and is awaiting final assembly and inspection by our partner, Kevin at TypePlus, after which it will depart for FSR.
The prototype unit has been received by FSR.
The replacement bespoke shipping boxes have now been dispatched and are en route to FSR.
03/02/2026
Switch plates for content creators have been ordered from Hypekeyboards: two aluminium, two carbon fibre, and one polycarbonate.
The modified Cherry switches from Tomb have been dispatched and are presently en route to Novelkeys and Alexotos.
04/02/2026
The solder MX PCB samples have undergone further comprehensive testing and what was originally thought to be a firmware issue has now been confirmed as a hardware matter. It was determined that tolerances are too tight for a number of components, resulting in a row shorting. A revised solder MX PCB is now being designed, with new prototypes to be ordered as soon as possible. Despite this, it has been decided that should content creators wish to use a solder MX PCB, they may still do so in order to highlight the acoustic character of a soldered build.
The replacement bespoke shipping boxes have arrived and meet the correct dimensions.
Three review units have been packed and are scheduled for pickup within the next two days.
The modified Cherry switches from Tomb have been received by Alexotos.
The switch plates for content creators have been dispatched from Hypekeyboards and are presently en route to Novelkeys and Alexotos.
06/02/2026
Three review units have been collected from FSR and are presently en route to our partners for content creation.
Following final assembly and inspection by Kevin at TypePlus, the fourth review unit has been dispatched to FSR.
The modified Cherry switches from Tomb have been received by Novelkeys.
The switch plates from Hypekeyboards have been received by Alexotos.
07/02/2026
The cyan review unit has been received by Chung-Li.
09/02/2026
The fourth review unit has now arrived at FSR with plates and authentication crests and has passed quality control, with only a minor note: after resizing to M3, the exterior screw holes are no longer anodised.
The silver review unit has been received by Novelkeys.
10/02/2026
The blue review unit has been received by Alexotos.
11/02/2026
The switch plates from Hypekeyboards have been received by Novelkeys.
12/02/2026
The green review unit has been packed and is scheduled for pickup within the next day.
13/02/2026
The green review unit has been collected from FSR and is presently en route to Alexotos for content creation.
16/02/2026
The prototype unit has been packed and is scheduled for pickup within the next day.
17/02/2026
The prototype unit has been collected from FSR and is presently en route to Mugen.kbd for content creation.
The green review unit has been received by Alexotos.
20/02/2026
The prototype unit has been received by Mugen.kbd.
The silver review unit has been repacked and is presently en route to LightningKeyboards for content creation.
21/02/2026
The blue review unit has been repacked and is presently en route back to FSR.
25/02/2026
The green review unit has been repacked and is presently en route to ExtraPriusPlease for content creation.
The silver review unit has been received by LightningKeyboards.
26/02/2026
The blue review unit has been received by FSR.
27/02/2026
The silver review unit has been repacked and is presently en route to TylerKeyboards for content creation.
28/02/2026
The green review unit has been received by ExtraPriusPlease.
01/03/2026
LightningKeyboards has been paid in full for content creation relating to the project.
02/03/2026
The silver review unit has been received by TylerKeyboards.
08/03/2026
The group buy has now concluded.
09/03/2026
Final sales figures have been received from Novelkeys and Typeplus.
10/03/2026
ExtraPriusPlease has been paid in full for content creation relating to the project.
The green review unit has been repacked and is presently en route back to FSR.
11/03/2026
Final production-run quotation requests have been issued for all aspects of the project.
A quotation for marine-grade stainless steel (A4) screws and 3M bumpons has been received, and the invoice settled in full.
13/03/2026
TylerKeyboards has been paid in full for content creation relating to the project.
The silver review unit has been repacked and is presently en route back to FSR.
14/03/2026
Final production order figures from Novelkeys and Typeplus have now been received, inclusive of additional units allocated for quality control.
15/03/2026
The marine-grade stainless steel (A4) screws and 3M bumpons have now been dispatched and are en route to FSR.
16/03/2026
The green review unit has been received by FSR.
17/03/2026
The marine-grade stainless steel (A4) screws and 3M bumpons have been received by FSR.
20/03/2026
The quotation for the production run units, comprising the enclosures, switch plates, and authentication crests, has been received and settled in full for FSR’s store, independent of Novelkeys and Typeplus. The following quantities specified pertain solely to FSR, with twenty-three enclosures commissioned, accompanied by twenty-three authentication crests, alongside a considered allocation of switch plates, consisting of twenty-three in carbon fibre, ten in transparent polycarbonate, and twelve in aluminium.
23/03/2026
The quotation for the production run units, covering the enclosures, switch plates, and authentication crests, has been received and settled in full for the Novelkeys store, independent of FSR and Typeplus. The following quantities specified pertain solely to Novelkeys: twenty-four enclosures commissioned, accompanied by twenty-four authentication crests, and a considered allocation of switch plates, including twenty-nine in carbon fibre, five in transparent polycarbonate, and fifteen in aluminium.
24/03/2026
The quotation for the production run units, encompassing the enclosures, switch plates, and authentication crests, has been received and settled in full for the Typeplus store, independent of FSR and Novelkeys. The following quantities specified pertain solely to Typeplus, with eight enclosures commissioned, accompanied by eight authentication crests, alongside a considered allocation of switch plates, consisting of eight in carbon fibre, and three in aluminium.
31/03/2026
The silver review unit has been received by FSR.
03/04/2026
The quotation has been received for the carry cases production run, and the order has been placed. Fifty per cent of the payment has been made, with the balance due upon completion of production.
06/04/2026
The production-run solder and hotswap MX PCB designs have been finalised by Gondolindrim.
15/04/2026
The quotation for the production run of MX PCBs, comprising both solder and hotswap, has been received and settled in full for FSR’s store, independent of Novelkeys and Typeplus. The following quantities specified pertain solely to FSR, with thirty-eight solder PCBs and eight hotswap PCBs commissioned.
17/04/2026
The quotation for the production run of MX PCBs, comprising both solder and hotswap, has been received and settled in full for the Novelkeys store, independent of FSR and Typeplus. The following quantities specified pertain solely to Novelkeys, with thirty-nine solder PCBs and fifteen hotswap PCBs commissioned.
The quotation for the production run of MX PCBs, comprising both solder and hotswap, has been received and settled in full for the Typeplus store, independent of FSR and Novelkeys. The following quantities specified pertain solely to Typeplus, with ten solder PCBs and two hotswap PCBs commissioned.
13/05/2026
Pre-production MX PCB samples have now been completed and are being prepared for shipment to FSR for in-person evaluation and verification.
The screws, bumpons, and colour samples have now been packaged and are scheduled for collection tomorrow.
14/05/2026
The pre-production MX PCB samples have been dispatched and are presently en route to FSR.
The screws, bumpons, and colour samples have now been collected from FSR and are presently en route to Dadesin for the production run.
18/05/2026
The screws, bumpons, and colour samples have been received by Dadesin.
The pre-production MX PCB samples have been received by FSR, and testing has been completed successfully. The go-ahead has been given for the remaining production run to proceed.
19/05/2026
The carry cases have completed production, with the remaining balance settled in full. Fifty-five carry cases have been dispatched and are presently en route to Dadesin.
25/05/2026
The MX PCB production run is now complete. A total of eighty-seven solder MX PCBs and twenty-five hotswap MX PCBs have passed factory quality control, been packaged, and dispatched to Dadesin.
28/05/2026
The MX PCBs have been received by Dadesin.
29/05/2026
The carry cases have been received by Dadesin.