Luna timeline
View the complete timeline of the Luna project, encompassing design developments, manufacturing updates, and release information. All dates are shown in the day/month/year format.
29/04/2025
Concept initiation.
03/05/2025
Public reveal.
07/05/2025
A quotation request for the prototype has been submitted.
10/05/2025
The quotation for Luna has been received.
11/05/2025
The prototype order has been confirmed, with fifty per cent of the balance paid at present and the remainder to be settled upon completion of production. The prototype is fabricated from A96063 aluminium alloy, featuring a machined finish, anodised in silver.
21/06/2025
Production of the prototype has now been completed.
09/07/2025
The prototype has been dispatched and is presently en route to FSR. The remaining balance of the invoice has also been paid in full.
11/07/2025
The prototype has now arrived at FSR and has been formally approved.
20/10/2025
An enquiry was submitted to a carry case manufacturer.
24/10/2025
The quotation has been received for the carry case.
02/07/2026
Final production-run quotation requests have been issued for all aspects of the project.
06/07/2026
MiKeyDigit has been commissioned to produce the product page renders and has received payment in full.