Spirit timeline

View the complete timeline of the Spirit project, encompassing design developments, manufacturing updates, and release information. All dates are shown in the day/month/year format.

 

17/01/2025

Concept initiation.

 

01/05/2025

Gondolindrim has been approached and confirmed as the MX PCB designer for the project.

 

23/03/2026

An enquiry was submitted to a carry case manufacturer.

 

03/04/2026

The quotation has been received for the carry cases, and the order has been placed in preparation for the production run. Fifty per cent of the payment has been made, with the balance due upon completion of production. The case will feature a sleek black exterior with black metal zippers engraved with our branding, complemented by a tan interior. The interior is custom-moulded specifically to fit Spirit, ensuring a secure and snug fit.

 

19/05/2026

The carry cases have completed production, with the remaining balance settled in full. Forty-five carry cases have been shipped to FSR.